SUMMARY
Use this guide to create a maintenance plan, complete maintenance work orders, and review maintenance history. Recording maintenance helps ensure recurring maintenance tasks are tracked and provides a complete history of completed work.
WHEN TO USE THIS
Use this guide if:
- You want to create a maintenance plan for a component.
- You need to complete a maintenance work order.
- You want to review completed maintenance activities.
Note: This is a legacy feature and for a more streamlined approach we recommending using activities
PREREQUISITES
Before starting:
- You have access to the Preventive Maintenance module.
- You have permission to create maintenance plans.
- The component or production line has been configured.
STEPS
-
Open the Maintenance Plans page
- Open the Preventive Maintenance module from the left-hand navigation menu.
- Select the Maintenance Plans tab.
-
Create a maintenance plan
- Click New Plan.
- Enter the required maintenance plan details.
- Select the appropriate Role.
- Choose Operator if the work order should be visible on the Register Stops page.
- Optionally add instructions.
- The instructions field supports clickable links to guides or other documentation.
-
Configure the maintenance trigger
Select the trigger that best matches your maintenance schedule.
Cycles
- Use this option to schedule maintenance based on production counts.
- Select the sensor that should track production.
- Enter the Target (the number of produced units before maintenance becomes due).
- Enter a Grace Period (the additional number of units allowed before the work order becomes overdue).
Example
- Target: 10,000 units
- Grace Period: 1,000 units
The work order becomes due after 10,000 units and overdue if it is not completed before 11,000 units have been produced.
Calendar
- Use this option to schedule maintenance on specific days or recurring calendar intervals.
Elapsed Time
- Use this option to schedule maintenance after a specified amount of elapsed time.
- Select which days the timer should be active.
- Configure the grace period before the work order becomes overdue.
Click Create to save the maintenance plan.
-
Review scheduled work orders
- After the maintenance plan has been created, a work order is automatically scheduled.
- For cycle-based plans, Factbird estimates the due date using historical production data.
-
Complete a work order
- Open the work order.
- Enter your initials.
- Add a comment describing the completed maintenance.
- Save the work order to mark it as completed.
-
Review the maintenance history
- Open the component.
- Select the Maintenance History button.
- Review previously completed work orders and their recorded details.
EXPECTED RESULT
After completing these steps:
- A maintenance plan has been created.
- Maintenance work orders are generated automatically according to the configured trigger.
- Completed maintenance activities are recorded in the maintenance history.
TROUBLESHOOTING
Issue: A work order has not been created.
Try: Verify the maintenance plan is active.
Try: Confirm the trigger conditions have been configured correctly.
Issue: A work order is overdue.
Try: Review the configured grace period.
- Try: Complete the work order to update the maintenance history.
Issue: The work order is not visible on the Register Stops page.
Try: Verify the maintenance plan role is set to Operator.
- Try: Confirm the work order has become due.
STILL NEED HELP?
Contact Support and include:
- The maintenance plan name.
- The trigger type (Cycles, Calendar, or Elapsed Time).
- The production line or component.
- Screenshots of the maintenance plan and work order.
RELATED ARTICLES