ANSWER

  • No. Changes to Validated Speed and Expected Speed only affect future production. Historical production data continues to use the speed values that were configured at the time the data was recorded. 
  • A workaround for this is to create a Batch "in the Past". Navigate to the batch creation interface and manually create a batch with a start and end time that match the historical period you want to adjust.

ADDITIONAL DETAILS

  • This preserves the accuracy and integrity of historical production reports.
  • Future batches and production calculations will use the updated speed values after they are changed.

LIMITATIONS (if applicable)

  • Historical production data cannot be recalculated by changing speed settings.
  • Speed changes only apply from the point they are saved onward.
  • Existing reports continue to reflect the original production conditions.